- Pre-Application Document, Notice of Intent, and Request to use the Traditional Licensing Process (submitted 8/06/2009)
- FERC letter authorizing use of TLP (issued 9/15/09)
- FERC letter to agencies regarding designation of non-federal representative to conduct informal endangered species consultation and Magnuson-Stevens Fishery Conservation and Management Act consultation (issued 9/15/09)
- FERC letter regarding designation of non-federal representative to conduct day-to-day section 106 consultation responsibilities (issued 9/15/09)
- FERC Notice of Intent (issued 9/16/09)
- Notice and transcript of Joint Meeting Held November 12, 2009 to discuss study issues and receive public and agency comment regarding the Grant Lake/Falls Creek Project.
- KHL files additional information: Confirmation of contact information for Kenai Hydro, LLC. Supplemental Information / Request of Kenai Hydro, LLC under P-13211, et al. (filed 12/17/09)
- KHL files Summary of Comments Received on the PAD and proposed studies for the Grant Lake/Falls Creek Project, FERC Project No. 13212/13211 (filed 2/8/10)
- Kenai Hydro, LLC Submits updated applicant contact information under P-13211, et. al. (filed 3/1/10)
- Kenai Hydro, LLC Submit 2009 Environmental Baseline Study Report, Supplemental Information for the Grant Lake/Falls Creek Project (filed 3/2/10)
- Kenai Hydro, LLC files Updated Project Description and Issues List for the Falls Creek (Project No. 13211) and Grant Lake (Project No. 13212) Hydroelectric Project (filed 5/3/10)
- FERC issues scoping document of environmental issues for an original license for the Grant Lake/Falls Creek Hydroelectric Project Nos. P-13212-001 and P-13211-001 (issued 5/11/2010)
- Kenai Hydro, LLC files Comments on FERC's Scoping Document 1 for the Grant Lake Hydroelectric Project (Project No. 13212/13211) (filed 7/6/10)
- Kenai Hydro, LLC files Revised Project Description and Updated Schedule for the Grant Lake Hydroelectric Project (Project No. 13212/13211) (filed 8/13/10) (Color version of Project Facilities Figure)
- FERC issues Scoping Document 2 for an original license for the Grant Lake/Falls Creek Hydroelectric Project Nos. P-13212-001 and P-13211-001 (issued 8/23/2010)
- Kenai Hydro, LLC files response to FERC's information request regarding the Grant Lake Project's consistency with current Forest Service Policy (filed 8-12-10)